2007 – BOTICELLI
Project description : Freestanding wall using secant hollow auger cast piles for the underground and below sea level car park for the Boticelli project
Client : SARL Botticelli
Worksite supervisor : Cabinet Cayrol
Cost of works : 130 000 000 FCFP
2013 – PUMPING STATION, AVENUE DE LA VICTOIRE (NOUMEA)
Project description: Secant auger cast pile wall (52 piles – 14m each). These works necessitated a guiding low wall. The wall shielded the excavation up to 7 meters and allowed us to work below sea level without water ingress.
Client : Mairie de Noumea (Noumea Town Hall)
Worksite supervisor : SOPRONER
Montant des travaux : 31 500 000 FCFP
2000 – LES STUDIANTINES RESIDENCE
Project description : Muscows freestanding wall consisting of :
– 17 bored concrete piles,
– Shotcrete wall with screed finishing between piles.
This permanent wall is the car park wall and supports the neighbouring building
Client : SCI Studiantines
Worksite supervisor : PROMOBAT
Cost of works : 9 000 000 FCFP