KNS, anchoring of the power plant massifs and micro-piles on the conveyor belt line (Vavouto)

 

Project description :

1065 tie rods measuring between 12 and 18 metres and 600 micro-piles for the foundations of the Vavouto / KNS nickel plant.

Client :

KNS

Worksite supervisor :

KNS Projet (Hatch Technip / KNS)

Location :

Coal-fired plant in Vavouto and for the conveyor belt on the Koniambo Massif

Reception date :

Février 2012

Cost of works :

990 000 000 FCFP

Expertise required :

Tie rods and micro-piles

Particularities of the project :

Project undertaken in partnership with SPIE Foundations (Investment of 330 000 000 FCFP)

Project with significant constraints

– Short time delay, mainly for the active anchor phase

– Works with environmental asbestos present which required specific prevention planning

– Very difficult access for installing the micro-piles in the Massif

– Joint venture and high client standards due to the international scale of the project